Wates had been in negotiations with the council to replace the cladding, windows and curtain walls at the estate and was undertaking preparation works since January 2019 under a “letter of intent”.
Its involvement came after the estate was evacuated
temporarily following the Grenfell Tower disaster amid fears that the blocks
were clad with dangerous ACM cladding.
This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.
Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.
Last year, it emerged that Camden Council has made a £130m
claim against the contractors involved in the refurbishment of the estate to
recover costs from Partners for Improvement in Camden (PFIC) and its principal
subcontractors – Rydon Construction, Rydon Maintenance, Faithful + Gould and
United Living South. PFIC is in liquidation.
Wates appeared to be lined up to remediate the estate but the council cabinet has now accepted a recommendation from council project officer Astrid Kjellberg-Obst to re-tender the work, already delayed because of covid-19.
In a letter sent to residents last month, Kjellberg-Obst
explained that on 17 March, Wates submitted its final offer but the recommendation
to the council cabinet was to reject it and to go back to market.
“This is because unfortunately despite many discussions, the
offer Wates provided to deliver the full programme of works was not what we
expected or wanted for residents. We made a commitment that we would provide a
gold standard of safety, designed with residents, and our view is we can’t sign
up to something that falls short of this.
“We know that the works will be significantly delayed
already because of covid-19 but if cabinet agree with our recommendation and
reject Wates’ current offer, the major works will be delayed for longer than
the pause caused by coronavirus. Depending on the cabinet decision this could
unfortunately be a delay of up 12 months while a new contract is awarded,” Kjellberg-Obst
explained.
She added that the final cost of the work increased and the council project team was worried that it would continue to increase during the contract. In addition, she said the designs “aren’t what we asked for”, citing the example of Wates’ proposal to fit a bar on the kitchen windows and specifying toughened glass for all windows which it said was safe "but can shatter". The letter also warned that the programme of works provided by Wates “is not detailed enough”.
Following the cabinet’s decision to re-tender the major
works, Wates last week began removing netting from scaffolding across the
estate at the Bray and Taplow towers. Removal of the netting on other blocks
was expected to be complete this week. From Monday this week (25 May) Wates
also started to remove or adapt wood from windows on the ground floor to let
more light in.
A spokeswoman for Wates Living Space commented: “Due to ongoing contractual commitments with the Council it would be inappropriate for us to comment at this time.”