Video | HS2 completes ‘innovative’ M6 bridge slide

https://www.youtube.com/watch?v=Yc-75UkL1Qc

HS2 engineers have completed a 17-hour-long operation to slide a 4,600-tonne viaduct across the M6, without closing the motorway.

While a previous slide required a weekend closure of the main carriageway, the team – led by HS2’s main work contractor Balfour Beatty Vinci (BBV) – worked with National Highways to develop a new ‘fully restrained’ process. This allowed the final section to be slid into place above the moving traffic. 

The team undertook a three-stage process to assemble and install the 315m east deck of the M6 South viaduct, which will carry high-speed trains heading to Birmingham and further north.

Register for free or sign in to continue reading

This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.

Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.

Story for CM? Get in touch via email: [email protected]

Latest articles in Video