News

Thames Tideway hit by nine-month delay and cost hike

The Thames Tideway project has been delayed by nine months and an additional £233m has been added to the project costs.

In an update to investors, trading company Bazalgette Finance said its latest modelling indicates that construction work is now likely to be completed in the first half of 2025, and costs are forecasted to hit £4.1bn.

The project’s annual report, published in June, stated that Thames Tideway’s cost estimate had risen to £3.9bn and handover had been pushed back three months to June 2024.

The impact of the coronavirus pandemic on operations has been cited as the cause of the latest delay.

The 25km ‘super sewer’ is being constructed by a Bam, Balfour Beatty and Morgan Sindall joint venture.

Story for CM? Get in touch via email: [email protected]

Latest articles in News