In pictures | Challenging installation of temporary bridge in Darley Abbey
Cristina Lago Deputy Editor
The temporary bridge, which opened last October, has been named 'Walter's Walkway’ by school children (Image: Mabey Hire)
A temporary bridge has been successfully installed in a Derbyshire village amidst complex space and access challenges.
The original bridge provided the historic village of Darley Abbey with local access across the River Derwent to the Darley Abbey Mills, an area with restaurants and small businesses.
However, the structure was condemned in May 2022 after safety concerns.
This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.
Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.
Derby City Council appointed temporary works specialist Mabey Hire to design, supply and install a provisional bridge.
“This was a huge and incredibly complex installation” (Image: Mabey Hire)
For this project, Mabey Hire deployed its Compact 200 (C200) modular footbridge system, a trademarked design developed by the company specifically for pedestrian applications.
C200 is quick and easy to assemble by hand or with light plant equipment and features steel mesh infill panels for added safety.
Challenging works
But despite the straightforward design of the C200 bridge, the installation works were particularly challenging due to the site’s geography.
“We were working with exceptionally tight tolerances – at one point, part of the crane was just a couple of metres away from a resident’s front door!” explained Lee Matthews, major projects manager at Mabey Hire.
A row of protected trees made the site constraints particularly challenging (Image: Mabey Hire)
The 45m-long temporary bridge was delivered to site in modular panels. It was assembled in skeleton form on a residential road and lifted into position by a 500-tonne capacity crane.
“This was a huge and incredibly complex installation, requiring all of our engineering team and in-house installation team’s expertise to plan and safely execute logistically,” Matthews added.
“Due to the location, it was decided that a crane-lift would be the safest approach but even that presented challenges. As well as the residential street being the location for the bridge assembly – a very tight space – the site also included a row of protected trees, which made the site constraints even harsher when considering the crane lift.”
The bridge was lifted into position by a 500-tonne capacity crane (Image: Mabey Hire)
The temporary footbridge was officially named ‘Walter’s Walkway’ following a competition where local school children suggested potential names for the bridge. It opened to the public in October 2022.
The November/December 2025 issue of Construction Management magazine is now available to read in digital format.
Powered Access
CM, in partnership with IPAF, has launched a new survey to explore the industry’s views and experiences with powered access machines on construction projects.
This is not a first step towards a paywall. We need readers to register with us to help sustain creation of quality editorial content on Construction Management. Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings. Thank you.