In pictures | Erith completes demolition of Sizewell A turbine hall
Cristina Lago Deputy Editor
Aerial view of the site in April 2025
Demolition contractor Erith has completed an 18-month project to fully demolish the turbine hall at Sizewell A nuclear power station, marking a milestone in the ongoing decommissioning of the site.
The football-pitch-sized hall has now been razed to the ground using innovative techniques, which allowed the project to be completed significantly faster than using traditional decommissioning and dismantling approaches.
The first overhead crane coming off the rails
The Office for Nuclear Regulation (ONR) said that its collaborative engagement with Nuclear Restoration Services (NRS), the site’s licensee, helped to achieve efficiency savings in time and money throughout the project, which began in autumn 2023.
This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.
Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.
Up to 700kg of explosives were used last November to debilitate the four reinforced concrete turbine bases on which two 65-tonne turbogenerators stood. It was the largest amount of explosives ever used on British soil at a nuclear site.
Erith dismantling the structure in February 2025
Recycled metal
High-reach cranes and excavators were then used to remove rubble from the weakened turbine plinths and tear down the rest of the concrete structure.
A total of 11,000 tonnes of metal were removed during the demolition and deplanting process, the majority of which will be recycled and sold on, with the money to be used to offset future decommissioning work, the ONR said.
About 35 miles of cable and more than 17,000 tonnes of concrete and rubble have been removed from the turbine hall, fire station and electrical annexe structures. It will be crushed, processed and reused for ongoing construction projects.
A concrete plinth that Erith weakened by explosives
The empty land that now lies where the flattened turbine hall once stood will eventually be restored and released for reuse.
Sizewell A was built in the 1960s and was officially opened in 1967. Its twin reactors were shut down at the end of 2006 after 40 years of electricity generation. The whole site is expected to be completely cleared by 2077.
The January/February 2026 issue of Construction Management magazine is now available to read in digital format.
Powered Access
CM, in partnership with IPAF, has launched a new survey to explore the industry’s views and experiences with powered access machines on construction projects.
This is not a first step towards a paywall. We need readers to register with us to help sustain creation of quality editorial content on Construction Management. Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings. Thank you.