HS2 takes NAO’s concerns about timetable and complexity on board

A total of 112,000 precast, steel fibre-reinforced concrete wall segments will line the HS2 Chiltern tunnel. (Image: David Hares (c) HS2 Ltd

HS2 has implemented seven of 14 recommendations made by the public sector spending watchdog, after it produced two reports warning about the timetable and complexity of the high-speed rail project.

The National Audit Office (NAO) produced a report in 2016 which found that HS2 Ltd had struggled to meet an overly ambitious timetable set for it by the Department for Transport, with the programme facing cost and schedule pressures. Phases 1, 2a and 2b of the project are expected to cost between £72bn and £98bn, based on 2019 prices.

A follow-up report in 2020 found that HS2 and the Department had underestimated the programme’s complexity and had not accounted for the level of uncertainty and risk in the programme.

Register for free or sign in to continue reading

This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.

Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.

Story for CM? Get in touch via email: [email protected]

Latest articles in News