Gateway 2 bottleneck set to be clear by January 

Gateway 2 bottleneck Image: Neil Lang via Dreamstime.com
Image: Neil Lang via Dreamstime.com

The Building Safety Regulator (BSR) has released its October update on Gateway 2 building approval applications.

In the report, BSR confirmed that it will work through the backlog of applications by January 2026.

The BSR’s newly-established innovation unit (IU) now handles 27 of the new‑build applications – comprising 6,192 housing units – and is achieving the mandated 12‑week service level agreements.

BSR has committed to completing the 91 legacy applications under the previous model by 31 December, covering 21,745  housing units.

Register for free or sign in to continue reading

This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.

Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.

Story for CM? Get in touch via email: [email protected]

Latest articles in News