Costain had previously won adjudication awards over the A465 Heads of the Valleys road for the Welsh government, having entered into the contract in 2015.
However, the Welsh government escalated a specific matter under
the dispute resolution mechanism in the contract relating to the responsibility
for design information for a specific retaining wall and whether it qualified
as a “compensation event”.
This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.
Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.
The arbitrator's decision found that responsibility for the
design information rests with Costain and, consequently, the additional costs
associated with the building of the retaining wall is not a compensation event
under the contract.
In a statement, the company said: “Costain is disappointed
by the arbitration award which reverses the ruling of previous adjudication
awards. The arbitration award, which determines a matter of principle only, and
not quantum, is non-appealable.
“Although the arbitration award relates to the liability for
the additional costs associated with the building of a specific retaining wall
under the contract, it has implications for the responsibility for design
information under the whole contract and therefore Costain's ability to recover
these costs.”
Costain is still in discussions with the Welsh government in
a bid to reach agreement on a final financial settlement for the roads job, and
to seek recovery of costs under the contract.
But it said that in light of the new decision, it would
include a £45m charge in its accounts.
The group will announce its half year results on 14
September 2020.