90% of cladding remediation complete or underway

Cladding remediation work accelerated in December 2020, with work started or complete on 90% (417) of all identified high-rise residential and publicly owned buildings in England, according to official figures.

As of the end of December 2020, the number of buildings where work to remove and replace unsafe aluminium composite material (ACM) had either been completed or had started increased by 31 – the highest monthly increase in 2020.

Building Safety Programme - progress of ACM cladding remediation work as of 31 December 2020 (Source: Ministry for Housing Communities and Local Government)

During 2020, 159 buildings started works, compared to 90 in 2019 and 111 in 2018.

Register for free and continue reading

This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.

Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.

Story for CM? Get in touch via email: [email protected]

Latest articles in News