CM Staff
GOLD: James Wood MCIOB - Morgan Sindall Construction
Project: Vandyke Upper School, Leighton Buzzard, Bedfordshire Scope: Construction of three-storey teaching block and remodelling and refurbishment of existing school, completed in 33 weeks Client: Vandyke Upper School Contract: JCT, design and build Value: £11m
This three-storey new-build project demanded a fearsomely fast construction programme to open in time for the new academic year. James Wood met it by turning to modular construction to achieve a 20-week improvement compared to a traditional build. By splitting the erection sequence for the 87 modules into two complete halves, he was able to start external critical path works earlier.
This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.
Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.
Andy Barlow MCIOB Skanska, Kingsweston SEN School, Bristol Finlay Black MCIOB Robertson Construction (Northern), Merkinch Primary School & Family Centre, Inverness Nigel Hayes Kier Construction, Treorchy Comprehensive School, Phase 3B Wayne Stokes Stepnell, The Cornerstone Academy, Poole Mark Turner Willmott Dixon, Hornchurch High School, Essex
James worked closely with the modules supplier to tailor the factory work processes so that risks associated with installations could be minimised. He also sent at least two team members to the factory every week to witness quality assurance processes.
James made major time gains in the new build’s ground by using the existing stone surface for the piling mat. Likewise, he tweaked site levels for four netball courts, eliminating hundreds of muck-away lorry movements, and changed the position of the attenuation tank to enable installation early in the programme.
On a super-tight programme, James delivered on time – handing over the new build fully commissioned and snag-free on the Friday, with students starting classes the following Monday – and to a standard that matched the client’s high expectations.
SILVER: Andy Mitchell MCIOB - Willmott Dixon
Project: Ropemakers’ Academy, Hailsham, East Sussex Scope: Construction of two-storey school, completed in 66 weeks Client: East Sussex County Council Contract: JCT 2016, design and build Value: £13m
On a difficult site, Andy Mitchell meticulously planned a fine success. He visualised the entire build in his head – from the piled foundations and concrete raft to the steel frame, composite floors, single-ply roof and brick cladding.
He engaged the supply chain with collaborative leadership and had thoroughly detailed the design before even getting to site. Changes to groundworks, drainage, roof details and swapping an in-situ concrete staircase for a precast one were some measures that improved the ease of build.
The project finished two weeks early, delivering budget savings and a level of quality that delighted the client.
The November/December 2025 issue of Construction Management magazine is now available to read in digital format.
Powered Access
CM, in partnership with IPAF, has launched a new survey to explore the industry’s views and experiences with powered access machines on construction projects.
This is not a first step towards a paywall. We need readers to register with us to help sustain creation of quality editorial content on Construction Management. Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings. Thank you.