Construction Management is the highest circulation construction-based publication serving the UK built environment.
Technical
Covid hospitals: Cardiff stadium’s biggest test
Will Mann
The coronavirus field hospitals presented a construction challenge like nothing before. Will Mann talks to the project managers on three of the hospitals, starting with Dragon’s Heart in Cardiff, where Mott MacDonald led a team including events specialist ES Global.
The Principality Stadium in Cardiff normally provides the
backdrop to Welsh rugby internationals. In March, it was picked as the venue
for a different kind of test – as one of the ‘field hospitals’ which were
hastily being constructed for coronavirus patients around the UK.
Dragon’s Heart, the name chosen for the facility, was unusual in requiring construction of a tented area inside the stadium to accommodate the clinical facilities. Its construction team was unusual too. Consulting engineer Mott MacDonald led the project team and gave the contractor job to a non-construction firm, events specialist ES Global.
Ciaran Willcocks, project director at Mott MacDonald, takes up the story: “We got the phone call at 3pm on Sunday 29 March. Over the next 12 hours, we pulled together the project team and the supply chain for the project. We were on site at 8am on Monday morning the next day with ES Global as contractor and architect BDP.
This is not a paywall. Registration allows us to enhance your experience across Construction Management and ensure we deliver you quality editorial content.
Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings.
Project managers: Mott MacDonald, Archus Main contractor: ES Global Architect: BDP Structural engineer: Momentum M&E engineer: Hoare Lea Tent installation: Nine Yards
“On that Monday, we talked through the project with various
stakeholders, including the Welsh government and NHS Wales. We agreed that by
the end of that day, a decision had to be made on the scope of the hospital so
work could get underway the next day. The CEO of NHS Wales gave the go-ahead at
6pm.
“We took that as formal confirmation and mobilised the team
to start work the next morning, Tuesday 31 March. We received our letter of
authority on Friday 3 April. NHS Wales deserves credit for making the decision
on the spot and issuing a substantial letter of credit to a contractor they’d
never heard of before – ES Global – to the tune of £2m.”
But Willcocks was confident the events contractor could
deliver, having worked with ES Global on the shooting venue for London 2012 at
Greenwich Park and the velodrome at the 2018 Asian Games in Jakarta, Indonesia.
“The major difference with Dragon’s Heart was constructing
the tented overlay space, which was not a require-ment at other hospitals like
ExCeL.
“This falls within the purview of ES Global, but not the
traditional construction contractor. We’ve had to source one of the biggest
tents in Europe for Dragon’s Heart, and construction contractors wouldn’t have
the contacts and knowledge for that job.”
Exterior of Cardiff’s Principality Stadium
Jeff Burke, owner of ES Global, explains the company’s
approach: “Our mobilisation plan went hand in hand with the design; one
depended on the other. We mocked up three or four possible tent layouts on the
pitch first; we needed to understand how different arrangements could work
depending on what products were available in the market the next day.
“This is a pragmatic approach which we’re very used to, and
it ensures we can deliver projects quickly, rather than being delayed waiting
for a specific bit of kit.”
Modular solution
The design and construction planning were necessarily
condensed, a process that would normally take two years completing in five
days, Willcocks explains. Where possible, modular construction was used.
“Most of the units are temporary plug and play, including
air-handling units, chillers, scaffolding and tents. We used a standard 2m x 1m
panel to build all headboards and bed partitions, and we’ve installed 6,000 of
those on the site.
In numbers: Dragon’s Heart Hospital
2,000 - maximum bed capacity
15,000 sq m - area of medical overlay tent
300km of cabling
80 tonne - weight of main oxygen tank
14,000 sq m of flooring
10MW of extra generator capacity
“The biggest tent measures 150m by 50m and there are also
four smaller tents, roughly 150m by 24m, and three around the edges, each about
100m by 10m each. Altogether, that is 15,000 sq m – around eight
times the size of the Glastonbury main stage.
“These were assembled using a 100-tonne crane, plus an army
of skilled operatives at pitch level, then a single cherry picker put the final
bolts in. There was almost zero working at height.”
However, the M&E provided a major technical challenge,
Willcocks says.
“There are no M&E connections whatsoever under the pitch
so we had to bring in our own – water, waste, oxygen, power, heat, cooling.
We’ve installed 10MW of generators inside the stadium –enough to power 15,000
homes – on top of the stadium’s existing 3.3MW of capacity. All this kit stands
on scaffolding around the covered tented area on the edge of the pitch. There
are also hundreds of cables and pipes feeding into the hospital, including
water pipes 10 inches thick.
Workers observe social distancing during the opening by Prince Charles
“Oxygen has been the limiting supply factor – valves,
terminals, fitters are all in national shortage, and most of all, the main
oxygen control panel. We’ve put in an 80-tonne main supply tank and a 40-tonne
ancillary oxygen tank.
“A massive amount of brand-new ducting has been put into
place. Installing the air handling was a major challenge. We fabricated these
huge steel ducts, 3m x 3m in diameter, which had to be ‘flown’ over the tents
and suspended from the stadium roof.”
Dragon’s Heart also makes use of space under the stands,
Willcocks explains.
“The concourses under the stands have been converted into
wards, and we had to board off the vomitories with acoustic panels, then
connect ductwork into this area so we could create a temperature-controlled
space.
“The home and away dressing rooms serve as office spaces,
the waste compactor room has been converted into a lead-lined CT scanner room
and fully functional blood laboratory, the press box is used for project
management meetings and I used the police cell when I had to make a private
call.”
Social distancing strategy
Bringing together a site workforce of over 1,000 and
delivering the work within a tight timeframe while maintaining social
distancing protocols has been a challenge, admits Willcocks.
“Finding the skills needed in those numbers was difficult.
We’ve worked 24/7 using a shift pattern but we couldn’t fill night shifts for
some of the work packages like fit-out – some 1,500 beds needed to be wired.
“We’ve installed enough generators inside the stadium to power 15,000 homes.”
Ciaran Willcocks, Mott MacDonald
“The social distancing puts an extra layer of complexity and
anxiety on everything, but people got used to it. With fit-out, we had
electricians, pipe fitters, carpenters and plumbers all working in the same
spaces – but also separated. And then this is complicated further when the army
arrives to put the beds together hot on the heels of the final fit out.”
He says the site workers were “mostly” happy with the
safeguarding measures.
“Clear communication from the NHS clinicians on site helped.
We took workers’ temperatures every morning, had handwashing facilities
everywhere, washed their clothes whenever they required it. We fed them 24/7
using a catering company that normally does rock concerts. We also opened up
four hotels nearby where many of them are staying.”
Dragon’s Heart became an operational hospital on 21 April,
with the first 300 beds in the stadium concourses. A further 1,200 in the
stadium bowl opened on 8 May, though total potential capacity is 2,000,
Willcocks adds.
“Nobody was happy that this needed to be built, but we’re glad to have been a part of it. It is one of the most interesting and gratifying engineering challenges I’ve ever had to work on.”
The January/February 2026 issue of Construction Management magazine is now available to read in digital format.
Powered Access
CM, in partnership with IPAF, has launched a new survey to explore the industry’s views and experiences with powered access machines on construction projects.
This is not a first step towards a paywall. We need readers to register with us to help sustain creation of quality editorial content on Construction Management. Registering also means you can manage your own CPDs, comments, newsletter sign-ups and privacy settings. Thank you.